ForgeCrest: Overhead and Volatile Demand

ForgeCrest Pump Components

Questions: 6 Answered:

Opens full screen, like the exam.

Question of 6 ForgeCrest: Overhead and Volatile Demand
ForgeCrest: Overhead and Volatile Demand Case-based question
The case

ForgeCrest makes precision impellers for water-treatment pumps. Its original annual manufacturing overhead budget was $480,000 for 60,000 machine hours. The company uses normal costing and one plantwide machine-hour allocation rate. Actual activity was 55,000 machine hours and actual manufacturing overhead was $425,000. All production was completed and sold by year-end, and beginning and ending work in process and finished goods were zero.

Two new customer industries have made monthly order volumes less predictable. Management wants spending plans for low, expected, and high activity levels. It is also considering activity-based costing because short custom batches require many more setups and inspections than long standard runs. Currently, senior executives set operating budgets without consulting shop supervisors.

Assumptions

  • Apply overhead using the original predetermined rate multiplied by actual machine hours.
  • With no inventories, the complete overapplied or underapplied balance is closed to cost of goods sold.
  • Activity levels remain within a range where variable rates and total fixed costs are stable.
  • The budgeting questions concern internal planning and evaluation rather than predicting exact future sales.

How much manufacturing overhead should ForgeCrest apply to its annual production? Enter a positive whole-dollar amount rounded to the nearest dollar.

USD

A whole number.

ForgeCrest has Overhead balance manufacturing overhead. Because all output was sold, before the closing adjustment its cost of goods sold is Unadjusted cost of goods sold and its gross profit is Unadjusted gross profit relative to the amounts after adjustment.

Arrange ForgeCrest's first ABC implementation in dependency order. For this project, management requires activity cost pools to be defined before drivers are selected, and rates to be approved before product assignment.

Dragging, or the arrow buttons, to reorder.

  1. Apply each approved activity rate to the driver units consumed by each product.
  2. Map overhead work into activity pools and collect the budgeted cost of each pool.
  3. Divide each pool's budgeted cost by its budgeted driver quantity to establish a rate.
  4. Choose a causal driver for each defined pool and estimate its budgeted quantity.

Saving…

Which TWO potential benefits justify ForgeCrest's ABC study? Select exactly TWO.

Select two answers. Selected 0 / 2

Answer

Which budgeting approach best supports ForgeCrest's request for comparable spending plans at low, expected, and high machine-hour volumes?

Answer

Which TWO outcomes could result if ForgeCrest includes shop supervisors in developing and reviewing operating budgets? Select exactly TWO.

Select two answers. Selected 0 / 2

Answer

The marks, the correct answers and the explanations appear as soon as the answers are submitted. Unanswered questions earn no marks.